One of Scotland's delayed and overbudget ferries needs repaired before it carries passengers, it has been revealed.

It is understood the Glen Sannox, which has an estimated total cost of between £145.5 million and £149.1 million, requires new cables and pipes due to rusting.

Shipyard workers at the nationalised Ferguson Marine will take parts from its delayed sister vessel - the Glen Rosa - to speed up the repairs, according to the Scottish Mail on Sunday.

Shipyard bosses have said transferring the parts from one vessel to the other will not have a knock-on effect on the delivery of the Glen Rosa.

However, emeritus Professor Keith Hartley, an economist and procurement expert at the University of York, questioned whether the second ferry will “ever be delivered”.

Glen Sannox was due to be handed over to CalMac to serve the Arran and Ardrossan route last month, but was delayed.


READ MORE: 

Glen Sannox suffers further blow as trials postponed due to blackout 

CalMac ferries ran to schedule in 7 days of 15 months period 

£1m paid in compensation to Caledonian Sleeper travellers 


Ferguson Marine said the vessel will be handed over “soon”, but no official date has been confirmed.

Professor Hartley, who also gave evidence to Westminster’s Scottish Affairs Committee, told the Mail on Sunday: “This sounds like the latest development in what is now a total fiasco.

“These ferries are massively overbudget and years delayed and this raises the questions over whether it is actually worth proceeding with the second ferry.

“At what point do you begin to ask if it will ever be delivered?”

The Glen Sannox, which was launched on November 21, 2017 by the then first minister Nicola Sturgeon, was originally due for delivery in 2018, but it has yet to enter service.

The vessel completed a number of successful sea acceptance trials following the completion of construction work at the nationalised shipyard in Port Glasgow, Inverclyde.

The shipbuilder’s interim chief executive said earlier this month the trials had been an “overall success”.

However, these newly identified repairs are a further setback in the handover which would allow the ferry to enter service on a key island route.

Cost of both vessels - which will serve the busy Arran and Ardrossan route - have more than tripled to at least £350 million in total and are expected to be delivered around six years late.

It is hoped the individual cost for the Glen Rosa will be kept below £150 million.

However, the total bill for both ferries were initially priced at £97 million.


READ MORE: 

CalMac reappointments have caused 'real anger' among islanders 

Ferry fares to increase by 'unwelcome' 10% in new year 


Work on both ships began in 2016 and they were originally due for delivery in 2018 but have faced significant design and construction challenges.

At the 2017 launch of the Glen Sannox, it had not been completely constructed, with the bridge and windows painted on and the funnels were not operational and instead only for show.

The dual-fuel engines on both vessels have also played a part in the delays, amid problems installing the liquified natural gas (LNG) system over the past year.

The state-owned shipyard found the process of cooling the pipes to the sub-zero temperatures necessary to load the fuel was taking longer than anticipated.

This meant they would no longer be able to meet the deadline for handover to the ferry-owning agency CMAL by September 30 as planned.

LNG needs to be kept at below -160C in order to remain in a liquid state.

Sue Webber, transport spokeswoman for the Scottish Tories, said: "Just when you think the SNP's ferries scandal can't get any worse, you're proved wrong. If it wasn't so serious it would be laughable.

"Ripping out parts of Glen Rosa to replace those on the Glen Sannox is robbing Peter to pay Paul.

"It's hard to believe Ferguson Marine's claim that this won't slow down the completion of Glen Rosa, but it seems their only priority is preventing any further hold-up on the Glen Sannox, which is already almost seven years late.

"Scotland's betrayed islanders are sick of the endless delays, incompetence, and excuses which SNP ministers have presided over, while taxpayers are carrying the can for the ever-spiralling costs.

"This is a prime example of why Scots are sick of politicians at Holyrood. Rather than obsessing over fringe issues, SNP ministers should focus their attention on delivering these ferries as promised."

A Ferguson Marine spokeswoman said: ‘Some parts have been taken from MV Glen Rosa for use on MV Glen Sannox.

‘Given we are due to handover Glen Sannox soon, this is a quicker approach than ordering replacement parts or fixing them. It will not delay the delivery of Glen Rosa.’

The Scottish Government has been asked for comment.